NCARB ARE 5.0 Project Management (PjM) - Project-Management Free Exam Questions

QUESTION NO: 1
When is a change order required?

Correct Answer: C Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 2
According to ATA owner-architect agreements, who is responsible for the cost of evaluating significant substitutions proposed by the contractor, subcontractors, or suppliers and the cost of making subsequent revisions to drawings, specifications, and other documentation?

Correct Answer: A Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 3
What is a critical factor in managing project risk?

Correct Answer: D Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 4
An architect is working on a design-build project for a large skyscraper. The architect has completed a conceptual design, finalized the contracts, and hired consultants. The schematic design phase is set to begin in one week.
Which items or tasks are important for the architect to complete during this time? Check the three that apply.

Correct Answer: B,C,D Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 5
During which project phase is the architect primarily responsible for preparing detailed construction drawings and specifications?

Correct Answer: D Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 6

Refer to the exhibit.
Construction documents are 75% complete for a design-bid-build project. As part of an architecture firm's quality control plan, the senior architect reviews the drawings and specifications for coordination. Following the review, the project architect distributes the senior architect's markups to the consultants.
What should the mechanical engineer do next to maintain quality control?

Correct Answer: C Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 7
During the preparation of the construction documents, it was noted that the survey inaccurately located the property line. Consequently, the parking layout had to be redesigned to fit within the corrected property boundary.
The architect's additional costs and associated delay are the responsibility of which one of the following parties?

Correct Answer: A Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).
QUESTION NO: 8
Which of the following is a key advantage of using Building Information Modeling (BIM)?

Correct Answer: A Vote an answer
Explanation: Only visible for Actual4test members. You can sign-up / login (it's free).

QUALITY AND VALUE

Actual4test Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.

Tested and Approved

We are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.

Easy to Pass

If you prepare for the exams using our Actual4test testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.

Try Before Buy

Actual4test offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.