BICSI Registered Communications Distribution Designer (RCDD) - RCDDv14 Free Exam Questions

QUESTION NO: 1
To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is concerned that the delivery of some program goals could be jeopardized.
What should the program manager do?

Correct Answer: A Vote an answer
QUESTION NO: 2
An ice cream company wants to introduce a new flavor to a new market. The executive sponsor requests a sampling for the test market and the sample group provides negative feedback As this type of program had previously been conducted by the company, the program manager questions whether similar results were experienced during testing.
What should the program manager do next?

Correct Answer: B Vote an answer
QUESTION NO: 3
External resources are required for a program. The program manager receives bids from multiple vendors and presents the top vendor to the program governance board. One program governance board member asks the program manager to select a vendor that was dismissed early in the selection process because they were not on the approved vendor list The program manager learns that this program governance board member has a personal connection to this vendor What should the program manager do?

Correct Answer: A Vote an answer
QUESTION NO: 4
A non-profit organization launched a program to reduce its dependence on regularly decreasing government funding sources. This program's goal was (o raise 50 percent of its operating expenses by selling its services to the for-profit sector. After three years, the goal was reached, deemed complete, and transitioned to operations.
Eighteen months later, the organization discovers that its dependence on government funds has now increased to 80 percent, even though its operating budget has largely stayed the same What should the program manager have done to avoid the issue of program benefits being unrealized after more than a year of implementation?

Correct Answer: A Vote an answer
QUESTION NO: 5
A program manager is developing a program management plan by integrating the plans of constituent projects.
During this effort, the program manager learns that a resource is critical to more than one component and there is a time overlap for their availability When creating the program resource management plan, what should the program manager do first?

Correct Answer: A Vote an answer
QUESTION NO: 6
A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated only 60 percent has been achieved What should the program manager do to ensure benefits realization?

Correct Answer: C Vote an answer
QUESTION NO: 7
To increase its presence and promote its products and services in new markets, a company begins to implement its new business strategy. The company's CEO endorses a new program to promote and support this strategy However before the program is formally initialed, this strategy must be aligned with the organization's strategic goals and objectives.
What should the program manager develop first?

Correct Answer: D Vote an answer
QUESTION NO: 8
A program completes all component projects and all identified benefits are being delivered However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters To ensure the realization of long-term benefits what should the program manager use?

Correct Answer: A Vote an answer
QUESTION NO: 9
When designing an underground conduit system, a single bend should be NO MORE THAN ________ degrees.

Correct Answer: C Vote an answer
QUESTION NO: 10
The risk manager completes risk response planning. The risk manager believes that to effectively address all eventualities, an additional action is required.
What should the program manager do next?

Correct Answer: B Vote an answer
QUESTION NO: 11
A program manager initiates a developmental program. Significant resources and funding are required (or early activities until the program cost and budget estimates are complete What should the program manager do to understand the financial environment?

Correct Answer: A Vote an answer

QUALITY AND VALUE

Actual4test Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.

Tested and Approved

We are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.

Easy to Pass

If you prepare for the exams using our Actual4test testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.

Try Before Buy

Actual4test offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.