PRINCE2 PRINCE2-Foundation (PRINCE2 Foundation written) exam is an internationally recognized certification exam for project management professionals. PRINCE2 (Projects IN Controlled Environments) is a widely adopted project management methodology that provides a structured approach to managing projects. The PRINCE2 Foundation written exam is designed to test the knowledge and understanding of the PRINCE2 methodology and its key concepts, principles, themes, and processes.
The PR2F exam covers a range of topics related to the PRINCE2 methodology, including the principles, themes, and processes of the framework. It also covers the roles and responsibilities of project management team members, as well as the key techniques and tools used in project management. Candidates must demonstrate their knowledge of these topics through a series of multiple-choice questions, which test their understanding of the PRINCE2 methodology and their ability to apply it to real-world scenarios.
NEW QUESTION # 251
Which product describes the method the project will use to engage with corporate, programme management or the customer?
- A. Benefits management approach
- B. Change control approach
- C. Communication management approach
- D. Quality management approach
Answer: D
NEW QUESTION # 252
Which describes a risk event?
- A. The sequence of events and actions that will be put in place if a risk occurs
- B. The area of uncertainty in terms of the threat or opportunity
- C. The achievement of a milestone on the project plan
- D. The derivation or sources of a potential risk to the project
Answer: B
Explanation:
Explanation
Reference http://prince2.wiki/Risk
NEW QUESTION # 253
Which theme establishes the mechanisms to control against baselines by providing a forecast for the project's objectives and continued viability?
- A. Plans
- B. Progress
- C. Business case
- D. Change
Answer: B
Explanation:
The Progress theme in PRINCE2 establishes mechanisms to control the project against its baselines by providing ongoing forecasts for the project's objectives and continued viability. This theme ensures that the project remains on track to deliver the expected outcomes and can adapt to changes when necessary.
= PRINCE2 7 Foundation handbook and online resources
NEW QUESTION # 254
Which is NOT a purpose of a Benefits Review Plan?
- A. Describe how to measure and confirm any benefits that are to be realised after the project is closed
- B. Define the period over which the cost-benefit analysis will be based
- C. Describe how to measure the performance of the project's products in operational use
- D. Define the scope, timing and ownership of the benefit reviews required
Answer: B
Explanation:
Section: Volume A
NEW QUESTION # 255
Which product records any project outcomes perceived as negative by stakeholders?
- A. Project Product Description
- B. Project Plan
- C. Communication Management Strategy
- D. Business Case
Answer: C
Explanation:
In PRINCE2, the Communication Management Strategy is the document that outlines how project communications should be managed. It includes how information will be disseminated amongst stakeholders and how feedback will be collected. Negative outcomes perceived by stakeholders are typically recorded as part of the feedback mechanism defined in the Communication Management Strategy. References:
PRINCE2 Foundation official guide and study material.
NEW QUESTION # 256
The project board Wants to consider whether td continue to operate in the same way, of Whether to change operations by means. of a project.
In which step of 'business case management technique should this be considered?
- A. Check
- B. Develop
- C. Confirm
- D. Maintain
Answer: B
Explanation:
The 'Develop' step in the 'Business Case Management' technique within PRINCE2 is where the rationale for the project is initially formulated. This includes evaluating whether current operations should continue as they are or if a change through a project could potentially enhance efficiency or effectiveness. This is the stage where strategic decisions about starting a project are made based on business justifications.
= PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation Top of Form
NEW QUESTION # 257
How many roles make up the Project Board?
- A. Four
- B. Three
- C. One
- D. Two
Answer: B
NEW QUESTION # 258
Which is a purpose of a quality register?
- A. To detail the number and type of quality activities to be conducted
- B. To identify corrective actions that are required after an audit by quality assurance
- C. To issue a unique reference number for each product
- D. To record the quality management approach for a product
Answer: A
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Quality#The_Quality_Register
NEW QUESTION # 259
Which is a true statement about time-driven controls?
- A. Time-driven controls take place when specific events happen
- B. An Exception Report is a time-driven control
- C. Time-driven controls are produced at the end of a stage
- D. Time-driven controls are used for monitoring the progress of Work Packages and management stages
Answer: D
NEW QUESTION # 260
Which is part of quality control?
- A. Produce quality records to show that the planned quality activities have been carried out
- B. Document the project's acceptance criteria in the Project Product Description
- C. Define the quality responsibilities of those involved in the production of the products
- D. Maintain the corporate organization's quality management system
Answer: A
NEW QUESTION # 261
Which is a purpose of the Business Case theme?
- A. Establish the controls to manage changes that may impact the project benefits
- B. Identify which role is responsible for producing the Business Case
- C. Identify the project'soutputs
- D. Establish a viable investment proposition
Answer: D
NEW QUESTION # 262
How is a Benefits Review Plan used in the Closing a Project process?
- A. Checked for inclusion of activities to confirm those benefits which cannot be measured until after project closure
- B. To gain approval for the post-project activities and transferresponsibility to corporate or programme management
- C. To capture the baseline measures against which to assess benefits
- D. To capture side-effects (beneficial or adverse) identified during post-project benefits reviews
Answer: A
NEW QUESTION # 263
What must be produced to meet the minimum requirements when applying the change theme?
- A. Records of the decisions made on all issues
- B. Status reports on all products being produced
- C. Documents recording the version of each product
- D. A change budget for the analysis of change
Answer: A
Explanation:
Section: Volume B
Explanation
NEW QUESTION # 264
What process aims to ensure accurate progress information is provided to the Project Manager?
- A. Directing a Project
- B. Managing a Stage Boundary
- C. Starting up a Project
- D. Managing Product Delivery
Answer: D
NEW QUESTION # 265
Identify the missing words in the following sentence.
The role of [ ? ] is assigned to the project manager if it is not allocated to another person.
- A. change authority
- B. senior user
- C. project support
- D. project assurance
Answer: C
Explanation:
Explanation
Reference http://prince2.wiki/Roles_and_responsibilities
NEW QUESTION # 266
Which is a benefit of using PRINCE2?
- A. Can be used to manage both projects and programmes
- B. Includes many of the proven planning techniques, such as critical path analysis
- C. Provides for the efficient and economic use of management time
- D. Is a method specifically designed for technical projects
Answer: C
NEW QUESTION # 267
Which is a key decision made during the 'directing a project' process?
- A. Approve the proposed project mandate
- B. Select and appoint the project executive
- C. Confirm that the benefits management approach addresses all expected benefits
- D. Approve the project manager role description
Answer: D
Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.greycampus.com/opencampus/prince-2-practitioner/purpose-of-directing-a-project- process-in-prince2
NEW QUESTION # 268
Which is an objective of the 'directing a project' process?
- A. To review and approve a project mandate
- B. To ensure corporate or programme management has an interface to the project
- C. To define how risks, issues and changes will be managed
- D. To obtain approval for completed products
Answer: B
Explanation:
Explanation
Reference http://prince2.wiki/Directing_a_Project#Objective
NEW QUESTION # 269
......