NEW QUESTION 66
Which new project roles are introduced with the SAP Activate methodology for the Agile delivery approach, compared to waterfall? 2 correct answers
- A. Product owner
- B. Integration lead
- C. Scrum master
- D. Design thinking coach
Answer: A,C
NEW QUESTION 67
What are two important approaches, based on the Control Center concept that SAP proposes to use for streamlined implementation and operations within Premium Engagements? There are 2 correct answers to this question.
- A. Always Connected
- B. Intelligent Enterprise
- C. Run SAP Like a Factory
- D. Build SAP Like a Factory
Answer: C,D
NEW QUESTION 68
In SAP Activate, what tool is used in the agile delivery approach during the Realize phase to make forecasts based on actual data?
- A. Release plan
- B. Product increment
- C. Project plan
- D. Burndown chart
Answer: D
NEW QUESTION 69
Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning? Please choose the answer.
- A. Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity
- B. Relative estimate in ideal person days that reflects the best estimate provided by the project team
- C. Product Owner's relative estimate of the effort that will be needed to implement the user story
- D. Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks
Answer: C
NEW QUESTION 70
Where can you check for the current roadmap of SAP Cloud ALM?
- A. SAP ONE Support Launchpad
- B. SAP Community
- C. SAP Support Portal
- D. SAP Help Portal
Answer: C
NEW QUESTION 71
Which new project roles are introduced with the SAP Activate Agile methodology? There are 2 answers to this question.
- A. Design Thinking Coach
- B. SCRUM Master
- C. Integration Lead
- D. Product Owner
Answer: B,D
NEW QUESTION 72
In which SAP Activate methodology phase does the team complete the Integration Validation? Please choose the correct answer.
- A. Explore
- B. Deploy
- C. Prepare
- D. Realize
Answer: D
NEW QUESTION 73
The hypercare period is part of which phase?
- A. Explore
- B. Go-Live
- C. Realize
- D. Deploy
Answer: D
NEW QUESTION 74
What does the cutover involve?
- A. Closing quality gate
- B. Transporting new product increment in the developmetn system
- C. Switching productive business operations from one system to another
- D. Presenting compelted User Story to key users
Answer: C
NEW QUESTION 75
What is the key difference between Notes and Requirements in the Change and Deploy capability of SAP Cloud ALM?
- A. Notes are created from tasks.
- B. Users can create a follow-up task that is actionable for Requirements.
- C. Requirements are created from tasks.
- D. Users can create a follow-up task that is actionable for Notes.
Answer: B
NEW QUESTION 76
What are some core objectives of business process monitoring? 2 correct answers
- A. to provide process update and change feedback
- B. to provide reverse business process analysis
- C. to provide transparency over end-to-end processes
- D. to increase business process execution quality
Answer: C,D
NEW QUESTION 77
In which SAP Activate methodology phase does the team complete the Transformation Strategy?
- A. Explore
- B. Deploy
- C. Prepare
- D. Realize
Answer: C
NEW QUESTION 78
What is the difference between the "new implementation of SAP S/4HANA Cloud" And the "new implementation of SAP S/4HANA transition path? There are 2 answers to this question.
- A. SAP S/4HANA uses the implementation guide (IMG) and the in-app extensibility option for Configuration and development, and SAP S/4HANA Cloud uses SSCUs and the side- by-side Extensibility option
- B. Upgrade of SAP S/4HANA cloud are managed by SAP, and upgrades of SAP S/4HANA are managed by the customer
- C. There are different roles in the application design and configuration workstream
- D. Different sets of workstreams are used for these transition paths
Answer: A,B
NEW QUESTION 79
Via which media does SAP provide ready-to-run systems for SAP S/4HANA deployment? There are 2 answers to this question.
- A. SAP App centre
- B. Blu-ray disks
- C. SAP cloud appliance library
- D. SAP Solution Builder tool
Answer: B,C
NEW QUESTION 80
How does SAP Cloud ALM provide guidance for implementation steps?
- A. Documentation management
- B. Project management timelines
- C. Resource planning
- D. Preloaded content that adheres to SAP Activate tasks
Answer: D
NEW QUESTION 81
......
SAP Certified Specialist - SAP Activate for Cloud Solutions Project Manager Free Update With 100% Exam Passing Guarantee: https://www.actual4test.com/E-ACTCLD-21_examcollection.html