NEW QUESTION 66
Which new project roles are introduced with the SAP Activate methodology for the Agile delivery approach, compared to waterfall? 2 correct answers

  • A. Product owner
  • B. Integration lead
  • C. Scrum master
  • D. Design thinking coach

Answer: A,C

 

NEW QUESTION 67
What are two important approaches, based on the Control Center concept that SAP proposes to use for streamlined implementation and operations within Premium Engagements? There are 2 correct answers to this question.

  • A. Always Connected
  • B. Intelligent Enterprise
  • C. Run SAP Like a Factory
  • D. Build SAP Like a Factory

Answer: C,D

 

NEW QUESTION 68
In SAP Activate, what tool is used in the agile delivery approach during the Realize phase to make forecasts based on actual data?

  • A. Release plan
  • B. Product increment
  • C. Project plan
  • D. Burndown chart

Answer: D

 

NEW QUESTION 69
Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning? Please choose the answer.

  • A. Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity
  • B. Relative estimate in ideal person days that reflects the best estimate provided by the project team
  • C. Product Owner's relative estimate of the effort that will be needed to implement the user story
  • D. Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks

Answer: C

 

NEW QUESTION 70
Where can you check for the current roadmap of SAP Cloud ALM?

  • A. SAP ONE Support Launchpad
  • B. SAP Community
  • C. SAP Support Portal
  • D. SAP Help Portal

Answer: C

 

NEW QUESTION 71
Which new project roles are introduced with the SAP Activate Agile methodology? There are 2 answers to this question.

  • A. Design Thinking Coach
  • B. SCRUM Master
  • C. Integration Lead
  • D. Product Owner

Answer: B,D

 

NEW QUESTION 72
In which SAP Activate methodology phase does the team complete the Integration Validation? Please choose the correct answer.

  • A. Explore
  • B. Deploy
  • C. Prepare
  • D. Realize

Answer: D

 

NEW QUESTION 73
The hypercare period is part of which phase?

  • A. Explore
  • B. Go-Live
  • C. Realize
  • D. Deploy

Answer: D

 

NEW QUESTION 74
What does the cutover involve?

  • A. Closing quality gate
  • B. Transporting new product increment in the developmetn system
  • C. Switching productive business operations from one system to another
  • D. Presenting compelted User Story to key users

Answer: C

 

NEW QUESTION 75
What is the key difference between Notes and Requirements in the Change and Deploy capability of SAP Cloud ALM?

  • A. Notes are created from tasks.
  • B. Users can create a follow-up task that is actionable for Requirements.
  • C. Requirements are created from tasks.
  • D. Users can create a follow-up task that is actionable for Notes.

Answer: B

 

NEW QUESTION 76
What are some core objectives of business process monitoring? 2 correct answers

  • A. to provide process update and change feedback
  • B. to provide reverse business process analysis
  • C. to provide transparency over end-to-end processes
  • D. to increase business process execution quality

Answer: C,D

 

NEW QUESTION 77
In which SAP Activate methodology phase does the team complete the Transformation Strategy?

  • A. Explore
  • B. Deploy
  • C. Prepare
  • D. Realize

Answer: C

 

NEW QUESTION 78
What is the difference between the "new implementation of SAP S/4HANA Cloud" And the "new implementation of SAP S/4HANA transition path? There are 2 answers to this question.

  • A. SAP S/4HANA uses the implementation guide (IMG) and the in-app extensibility option for Configuration and development, and SAP S/4HANA Cloud uses SSCUs and the side- by-side Extensibility option
  • B. Upgrade of SAP S/4HANA cloud are managed by SAP, and upgrades of SAP S/4HANA are managed by the customer
  • C. There are different roles in the application design and configuration workstream
  • D. Different sets of workstreams are used for these transition paths

Answer: A,B

 

NEW QUESTION 79
Via which media does SAP provide ready-to-run systems for SAP S/4HANA deployment? There are 2 answers to this question.

  • A. SAP App centre
  • B. Blu-ray disks
  • C. SAP cloud appliance library
  • D. SAP Solution Builder tool

Answer: B,C

 

NEW QUESTION 80
How does SAP Cloud ALM provide guidance for implementation steps?

  • A. Documentation management
  • B. Project management timelines
  • C. Resource planning
  • D. Preloaded content that adheres to SAP Activate tasks

Answer: D

 

NEW QUESTION 81
......