Exam PSP Topic 2 Question 214 Discussion

Actual exam question for ASIS's PSP exam
Question #: 214
Topic #: 2
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

Suggested Answer: D Vote an answer

* Column Pour Requirements:
* Each column pour requires 60 lifts per day.
* Crane Capacity:
* Each crane can perform 35 lifts per day.
* Determine Minimum Cranes Required:
* Minimum Cranes = Column Lifts ÷ Crane Capacity = 60 ÷ 35 # 1.71 cranes.
* Since partial cranes cannot be used, round up to 3 cranes.
* Cross-Verification:
* Option A (2 cranes): Incorrect. Insufficient lifts per day.
* Option B (1 crane): Incorrect. Infeasible.
* Option C (4 cranes): Incorrect. Exceeds requirement.
* Option D (3 cranes): Correct. Satisfies lift requirements efficiently.
References:
* PSP Study Guide (2019), Sections on Equipment Productivity and Resource Allocation.
* AACE Recommended Practices, RP 10S-90.

by Kirk at Aug 25, 2026, 04:41 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.