Exam L4M3 Topic 3 Question 130 Discussion

Actual exam question for CIPS's L4M3 exam
Question #: 130
Topic #: 3
Carillion Ltd is a major construction contractor in the UK. The company commits to continuous improvement and sets out a performance management program that is integrated across the organisational, individual, and supplier levels. To ensure that the suppliers acknowledge the program, every time negotiating the contract terms with suppliers, the procurement team of Carillion appends a performance management framework to the draft document as a schedule. Is the action of procurement team appropriate?

Suggested Answer: C Vote an answer

Performance management framework often consists of KPIs, targets and consequences that arise from achieved scores. To ensure that the framework has binding effect on contracting parties, it should be developed, appended to the main contract document and agreed by both parties. So the answer should be
"Yes, because the framework should have legal standing as a part of contract".
Reference: CIPS study guide page 11-14
LO 1, AC 1.1

by Donna at Jul 09, 2026, 07:06 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.