Exam Construction-Manager Topic 1 Question 16 Discussion

Actual exam question for CMAA's Construction-Manager exam
Question #: 16
Topic #: 1
As the owner's rep, you are providing on-site construction management services to a municipality for their new design-build city mall project.
During your review of the design-build team's schedule update, you discover the project is five weeks behind schedule. What is your recommendation to the owner regarding the document needed from the design-build team to correct the situation?

Suggested Answer: A Vote an answer

According to theCMAA Standards of Practice (Chapter 4 - Time Management), when a schedule update shows significant delay or variance, the CM should require the contractor or design-build team to prepare a recovery plan. The SOP explains:
"If schedule performance indicates delay or slippage beyond acceptable limits, the contractor shall prepare a recovery schedule or recovery plan demonstrating the specific actions to be taken to regain lost time and complete the project within the contract duration." Thebaseline scheduleestablishes the original plan; it is not revised to reflect recovery actions. Ashort interval schedulemay assist with detailed weekly planning, but the required formal corrective document is the recovery plan.
References (CMAA Construction Manager Documents / Study Guide):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 4 - Time Management, Section "Schedule Updates and Recovery Plans." CMAA CM Study Guide, Time Management Domain, Objective 4.3: "Evaluate schedule performance and develop recovery plans when required."

by Joanna at Mar 31, 2026, 04:45 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.