Exam Construction-Manager Topic 1 Question 48 Discussion

Actual exam question for CMAA's Construction-Manager exam
Question #: 48
Topic #: 1
Float, date, and duration are examples of

Suggested Answer: B Vote an answer

According to theCMAA Construction Management Standards of Practice (SOP)underChapter 4 - Time Management, "schedule parameters" are quantitative data or attributes that define and control the time-based characteristics of project activities.
CMAA identifies parameters such as:
Dates(start and finish)
Durations(planned time to perform an activity)
Float or slack(available time flexibility within the schedule)
These are fundamental "parameters" because they define measurable scheduling characteristics rather than structural logic or relationships. In contrast, "logic elements" refer to the dependencies between activities, and
"constraints" impose limitations or conditions (such as "must finish by" or "start no earlier than").
Therefore,float, date, and durationare examples ofschedule parameters.
References (CMAA Documents):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 4 - Time Management, Section: "Scheduling Fundamentals." CMAA CM Study Guide, Time Management Domain, Objective 4.2: "Identify schedule elements and parameters."

by Sarah at Mar 17, 2026, 05:20 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.