Which of the following are deliverable's during the Inception Phase of a project?
Choose 2 options.

Suggested Answer: A,C Vote an answer

The correct answers are A. Conceptual Sprint Plan and C. Estimated User Stories because both are standard planning and readiness deliverables associated with the Inception phase of a Guidewire InsuranceSuite project. Inception is the phase where the team establishes delivery structure, confirms scope, prepares for iterative execution, and develops enough requirement detail to support planning and estimation.
A Conceptual Sprint Plan belongs in Inception because the project team needs an initial view of how work will be organized across iterations or sprints. At this point, the plan is usually high-level rather than fully detailed, but it is essential for aligning priorities, sequencing major work items, and preparing the project for execution.
Estimated User Stories are also a key Inception deliverable. During this phase, business needs are translated into user stories and then sized or estimated so the team can understand effort, support sprint planning, and validate that the project scope is achievable within constraints. Estimation helps connect business priorities to delivery capacity and is one of the major outcomes of early planning.
The other options are less appropriate as primary Inception deliverables in this context. Process Maps may sometimes be used as analysis aids during requirements work, but they are not typically emphasized as the core phase deliverables being asked about here. Detail Design Document (DDD) is more closely associated with deeper solution design and implementation detail, which generally occurs after Inception as requirements become more refined and the team moves further into execution.
For Guidewire project methodology, Inception focuses on building a delivery foundation. Therefore, when asked which items are deliverables of this phase, the best answers are Conceptual Sprint Plan and Estimated User Stories .

by Jerome at Jul 03, 2026, 11:58 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.