Exam ISO-21502-Lead-Project-Manager Topic 1 Question 29 Discussion

Actual exam question for PECB's ISO-21502-Lead-Project-Manager exam
Question #: 29
Topic #: 1
Scenario:
Oakniture is a furniture manufacturer located in Bristol, England. It is known for its kitchen tables made out of different types of wood, such as chestnut, walnut, and oak. In early 2022, Lana, one of the senior researchers of the company, conducted a feasibility study to determine if there is a market for oak wood coffee tables, which indicated that the demand for oak wood coffee tables is relatively high. As such, Lana prepared a project brief and presented it to the top management of the company. The project brief included information on the project context and project objectives. After several discussions, the top management agreed that the project should be undertaken, but lastly, they asked Lana about the project duration. Lana claimed that the project duration cannot be determined and such information was not provided in the project brief; however, she added that the project duration will mainly depend on the competencies of the project team and on Oakniture's suppliers of wood.
Following that, the top management initiated the project and assigned Tom, the operations director, as the project manager, and Lana as the project sponsor. To manage the project, they decided to use the guidelines of ISO 21502.
Initially, Tom defined the governance and management framework alone, and then he mobilized the team and assigned the roles and responsibilities to each team member. In addition, Tom and the project team identified the stakeholders and developed the project plan. To ensure effective management of each project phase, Tom used a work breakdown structure (WBS) to organize project activities. Tom presented the project activities in the WBS by linking task dependencies and showing project milestones. In addition, Tom calculated the duration of each work package by determining the early start and early finish dates. Regarding the relationship between work packages, Tom required the project team to perform tasks in the predetermined order, regardless of any resource shortages they might experience.
A week after the project implementation began, Tom collected and analyzed data regarding the progress of the project. To keep everyone up to date, he held a meeting with Lana and project stakeholders.
Question:
Scenario 4 states that Tom presented the project activities in the WBS by linking task dependencies and showing project milestones. Which WBS format did Tom use?

Suggested Answer: B Vote an answer

The correct concept is Gantt chart . Tom presented project activities by showing dependencies and milestones, which is characteristic of a Gantt chart. A Gantt chart is a schedule presentation tool that displays activities or work packages along a timeline and can show start dates, finish dates, durations, dependencies, progress, and milestones. Although the scenario says Tom used a WBS to organize project activities, the description of linking task dependencies and showing milestones goes beyond a pure WBS structure and aligns with schedule visualization. A flowchart would show process flow, decision points, or logical sequencing, but it is not the best format for displaying a time-based project schedule with milestones. A WBS normally decomposes project scope into deliverables and work packages; it does not, by itself, show chronological scheduling unless integrated with schedule tools. In practical project planning, a WBS is often used first to structure the work, and then a Gantt chart is used to display the timing and dependencies of that work. The source question asks this directly after stating that Tom linked task dependencies and showed milestones.
Reference topics: work breakdown structure, Gantt chart, schedule visualization, dependencies, milestones, activity sequencing.

by Christine at Oct 05, 2026, 11:58 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.