What do you need to know about the SAP S/4HANA Conversion Guide? Note: There are 2 correct answers to this question.
You are performing an SAP S/4HANA conversion. When does the silent data migration (SDM) take place?
What can you achieve by setting the SUM parameter "migration_only" to 1 in parameter file SAPup_add.par?
Please choose the correct answer.
Response:
You are executing as SAP S/4HANA Conversion with scenario strategy Standard. When will the shadow instance be stopped for the last time?
You are upgrading a three-system landscape DEV - QAS - PRD. The upgrade project contains a Unicode conversion. You have already upgraded the DEV and the QAS system but not yet the PRD system. What do you need to consider? Please choose the correct answer.
You are performing an upgrade with SUM using DMO to an AS ABAP 7.50 based SAP system. You entered a specific number of R3Ioad processes during Roadmap step "Extraction".
Where can you change this during the migration via the Utilities option of the SUM UI?
There are 2 correct answers to this question
Response:
You want to perform custom code check via ABAP test cockpit in preparation of your SAP S/4HANA conversion? What kind of SAP System can you use to generate the custom code migration worklist?
You are running an SAP ECC system.
For which of the following activities does SUM allow you to use the near-Zero Downtime Maintenance (nZDM) capabilities?
Note There are 3 correct answers to this question
You are performing an inplace SAP S/4HANA conversion including DMO. What is the latest point in time when you can reset the procedure without losing data?